Lifts & Escalators Status
Report
Date: 14
January 2004
1. Lifts & Escalators Returned to Service since Last
Report
Waterloo (Escalator No.17)
returned 24 December 2003
2. Lifts Currently Booked to Be Out
Of Service
Goodge Street (Lift No.4) until
19 January 2004
3. Escalators Currently Booked To Be
Out Of Service
London Bridge (Escalator No.19)
until 19 January 2004
Green Park (Escalator No.1)
until 19 January 2004
Balham (Escalator No.3) until 4
February 2004
Gants Hill (Escalator No.2)
until 10 February 2004
Clapham South (Escalator No.1)
until 14 February 2004**
Marylebone (Escalator No.3)
until 26 February 2004
Bank (Escalator No.4&5)
until 14 March 2004
Brixton (Installation of a new
escalator) until 15 March 2004*
Warren Street (Escalator No.7)
until 27 March 2004
Moorgate (Escalators No.6) until
5 June 2004
Oval (Escalator No.2) until 14
April 2004
Warwick Avenue (Escalator No.2)
until 16 April 2004
Wanstead (Escalator No.3) until
11 May 2004
Tottenham Court Road (Escalator
No.3) until 1 June 2004
Embankment (Escalators
No.9&10) until 11 October 2004
Kings Cross (New escalator no.8)
until 5 December 2004
4. Lifts & Escalators Coming Out
Of Service Over The Next Three Months
St.Pauls (Escalator No.5) from
18 January 2004 to 30 March 2004
Bond Street (Escalator No.8)
from 19 January 2004 to 29 July 2004
London Bridge (Escalator No.13)
from 20 January 2004 to 5 February 2004
Piccadilly Circus (Escalator
No.11) 2 February 2004 to 9 April 2004
London Bridge (Escalator No.20)
from 6 February 2004 to 23 February 2004
Tooting Broadway (Escalator
No.3) from 12 February 2004 to 23 August 2004
Clapham North (Escalator No.1)
from 26 February 2004 to 7 September 2004
Marylebone (Escalator No.1) from
27 February 2004 to 22 September 2004
Elephant & Castle (Lift
No.1) from 5 March 2004 to 7 March 2004
Turnpike Lane (Escalator No.3)
from 5 March 2004 to 29 September 2004
Bank (Lift No.3) from 7 March
2004 to 10 March 2004
Gants Hill (Escalator No.1) from
8 March 2004 to 17 September 2004
Caledonian Road (Lift No.4) from
12 March 2004 to 14 March 2004
Borough (Lifts 1&2, one at a
time) from 18 March 2004 to 9 June 2004
Bank (Escalator No.1) from 22
March 2004 to 5 July 2004
Charing Cross (Escalator No.3)
from 29 March 2004 to 5 July 2004
St.Paul’s (Escalator No.4) from
5 April 2004 to 21 June 2004
* This work has been delayed due
to power problems and other related station works.
** This escalator is behind
scheduled due to technical problems which have held up work.